Summary
Supervisors Andahl and Stopper blasted years of delays on paving HartVixen and Baldwin Roads, pushed out again due to water district coordination — possibly to 2028 — with risk of losing state grant money.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Apr 14, 2026.
Impact analysis
Delays could cost the county state grant funding it may not recover.
Residents of Districts 2 and 5 once paving is finally completed.
Residents of Districts 2 and 5 continue driving on deteriorated roads while projects slip again.
Mentions & discussions (2)
Board of Supervisors - Regular Meeting — April 14, 2026
Supervisors Andahl and Stopper blasted years of delays on paving HartVixen and Baldwin Roads, pushed out again due to water district coordination — possibly to 2028 — with risk of losing state grant money.
Board of Supervisors - Regular Meeting — February 10, 2026
A Valley Springs resident presented a signed petition saying his 600-foot street hasn't been paved or sealed since 1990 and he's never gotten answers from Public Works or his supervisor.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Calaveras County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.